City of Saginaw MI -
Michigan Avenue

What:

The 2013 Michigan Avenue utility replacement and road resurfacing project is a continuation of the work begun in 2012. Previously underground utility work, select curb and gutter replacement, road resurfacing, sidewalk and ramp replacement was completed on Michigan Avenue from Stephens to Remington. In 2013, the work will continue on Michigan Avenue from Remington to State with extensive work being completed at the Michigan Avenue and West Genesee Avenue intersection to improve traffic lane alignment and traffic signal layout. Michigan Avenue traffic will be maintained; however, with lane restrictions in effect the Right-of-Way Division suggests travelers utilize the posted detour route.

When:

Tentatively scheduled to begin April 23, 2013. Proposed "open to traffic" on September 27, 2013. Right-of-way work to be completed on or before October 25, 2013.

Funding:

$3,070,000 estimated

  • Federal STP - $750,000
  • Water Surplus - $125,000
  • Water Bond - $1,325,000
  • ACT 51 - $250,000
  • Sewer Surplus - $300,000
  • Federal Safety Funds - $320,000

Contractor:

Champagne & Marx Excavating, Inc., 1445 Liberty Road, Saginaw, MI

Contact person:

Beth London, City Engineer - 989-399-1311

On-site contact person:

Right-of-Way inspection staff are on-site during construction activity and can be identified by looking for a green or orange truck with a city logo on the door.

Explore our Projects | Services | Resources

advertisement
advertisement

Parking Regulations in the City


SGTV LIVE STREAM:

Did you know?
The City of Saginaw's TV station (SGTV) is now live online, 24/7? Visit www.saginaw-mi.com/tv
or
visit our Youtube channel


FREEDOM OF INFORMATION ACT

The Freedom of Information Act (FOIA) rules have changed. To see how the City of Saginaw is now handling FOIA requests, please visit our new FOIA page.
LEARN MORE


advertisement

ROAD CONSTRUCTION:
There are no planned construction projects to display at this time.
SEE MORE